Study of the measuring system of the aqueduct network of Athens - Phase 1

[proj_id=57]

Duration: June 1990–December 1990

Budget: 9 000 000 DRS (about €44 555)

Commissioned by: Water Supply and Sewerage Company of Athens

Contractor: Department of Water Resources, Hydraulic and Maritime Engineering

Project director: Th. Xanthopoulos

Principal investigator: J. Gavriilidis

The objective of Phase 1 of the project is the testing of the reliability of the existing measuring system of the aqueduct network of Athens and the initial approximate estimation of the discharge capacities of the aqueducts.

Documents: