Duration: February 2024–May 2024
Budget: €29 500
Commissioned by: Hydroelectric Power Plants Operation Department
Contractor: Department of Water Resources and Environmental Engineering
Project director: A. Efstratiadis
Principal investigator: N. Mamassis
The project aims at the development of a suitable computational infrastructure for the hydrodynamic simulation of the hydrosystem downstream of Asomata Dam, in Aliakmonas River. This will be applied for various outflow scenarios through the hydroelectric plant and the dam spillway, which will be the upstream boundary of the study area, extending over about 2800 km2, of which approximately 2200 km2 are occupied by the catchment of the so-called Peripheral Trench (T66). The final product will be a computer system for one-dimensional analysis, in a HEC-RAS environment, and the associated data infrastructure, as backgrounds for the hydrodynamic simulation and, eventually, flood risk assessment across the vulnerable areas downstream of Asomata dam.